MrC
Here's a question for you. When you are in resource view you get a
listing of all resources with assigned tasks under them...ie
Joe Bloe
-task 1.1.1
-task 3.1.1
What I also need to see is the related summary tasks so the example would be
Joe Bloe
-task 1
-task 1.1
-task 1.1.1
-task 3
-task 3.1
-task 3.1.1
Is there a way to do this in views or with a report.
Thanks....