R
robertpoddar
Hi,
I am stuck up with my project planning and need to complete asap. I have a
particular resource, who is on leave from the 19th to the 22 Oct and his
tasks starts on the 5th Oct . The duration of the task is 50days.
I go to the Changer Working time and select the particular resource to nark
the days he is on holiday, but my end date does not shift accordingly,
irrespective of whether i am selecting the days as holiday or not.
Am i missing something?? I am using Project 2003 Standard version.
Any help would be greatly appreciated.
I am stuck up with my project planning and need to complete asap. I have a
particular resource, who is on leave from the 19th to the 22 Oct and his
tasks starts on the 5th Oct . The duration of the task is 50days.
I go to the Changer Working time and select the particular resource to nark
the days he is on holiday, but my end date does not shift accordingly,
irrespective of whether i am selecting the days as holiday or not.
Am i missing something?? I am using Project 2003 Standard version.
Any help would be greatly appreciated.