resources for summary tasks

J

jen

I am trying to look at my resource allocations in the upper tier summaries.
If I have a 1.1 "summary task" with sub tasks 1.1.1 throught 1.1.5 and I load
all my resources in the 1.1.1 through 1.1.5 tasks. How can I look at a roll
up of the resources to the summary task of 1.1?? It rolls up the hours and
the $$$, but it doesn't break out the hours of different personel. I seem to
only be able to access that on the lower level tiers.

Thanks!
 
R

Rod Gill

Except for admin tasks such as project management, it is poor practice to
assign resources to Summary tasks. For overviews, use the Resource or task
Usage Views.
 
J

Jan De Messemaeker

Hi Jen,

You can try as many times as you like, the answer won't change I'm afraid.
This is not possible without a VBA procedure, sorry.
 