Is there a way that I can limit the resources that someone can assign to a
task to the resources that I have already included on the resources page? I
have each existing employee and their pay rate on the resource page, but if I
am typing a task, tab to the resource field, and begin typing a first name of
an employee, then tab out, it add that first name as a new resource
 
D

Dale Howard [MVP]

Doug --

You cannot totally prevent this behavior in the software, which is the
default behavior by the way, but you can at least get the software to warn
you before adding a new resource to the project. Here's how:

1. Open a project
2. Click Tools - Options
3. Click the General tab
4. Deselect the "Automatically add new resources and tasks" option
5. Click the "Set as Default" button
6. Click OK

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top