Resources vs tasks tracking

M

Martin Lemay

The standard Gantt chart shows the tasks and associated resource over the
specified duration.

I'd like to be able to see a gantt chart showing the resources and their
associated tasks over time. It would show how the resource is used for the
time period

Thx
 
J

Jim Aksel

The best project can do for you is the Resource Usage View. On the menu
View/Resource Usage...
What you will see is a listing of each resource. Subodinate to that will be
each task assigned to that resource. On the right side will be a calendar.
However, no Gantt bars are available --- instead there are columns of numbers
representing hours for the time periods specified.
 
M

Martin Lemay

The best way I found is the use of the Report / Assignments / Whos Does What
When...my only problem is I can not export the report into Excel or other
file. I can only print it.
 
J

Jim Aksel

Yes, the reporting features of Project2003 and less are not robust. Project
2007 does have a much better export functionality to Excel.
 
J

Jim Aksel

I thought of one more thing you may want to try. This requires there be only
one resource for each task (which is probably a fatal flaw...)

On the Gantt view, insert a column called Resources. Go to Project/Group
By.../Customize Group By...

Select Groupt by Resource name. You now have a Gantt chart for each
resource combination. However, it does not respect the outline structure of
the schedule.
 