J
Joe
I have a development project plan I am managing. I have a developer who has
4 coding task to complete, which start on the same day. I don’t care what
order he completes these task items, so he can work on all 4 items for 2
hours a day or any combination. These task items have different durations.
Lets say they are t1=10hrs., t2=14 hrs., t3=20 hrs., t4=10 hrs. I would like
to set up the plan with this resource assigned to all 4 task items at 25%
utilization. The problem is after he is finished with t1 and t4, the plan
will still only have him at 25% utilization for t2 and t3, even though he
technically should be 50% utilization. So instead, I have the resource
assigned to the 4 task at 100% utilization, with each task dependent on the
other starting from t1. I really don’t like this method because it makes the
plan look like they are dependent on each other, but they really are not.
I thought of manually adjusting the hours after the task is done to make the
resource fully utilized, but it is a manual and tedious process, with over 20
developers, it is unmanageable.
Does anyone have this issue and have a better suggestion on how to handle
this?
Joe
4 coding task to complete, which start on the same day. I don’t care what
order he completes these task items, so he can work on all 4 items for 2
hours a day or any combination. These task items have different durations.
Lets say they are t1=10hrs., t2=14 hrs., t3=20 hrs., t4=10 hrs. I would like
to set up the plan with this resource assigned to all 4 task items at 25%
utilization. The problem is after he is finished with t1 and t4, the plan
will still only have him at 25% utilization for t2 and t3, even though he
technically should be 50% utilization. So instead, I have the resource
assigned to the 4 task at 100% utilization, with each task dependent on the
other starting from t1. I really don’t like this method because it makes the
plan look like they are dependent on each other, but they really are not.
I thought of manually adjusting the hours after the task is done to make the
resource fully utilized, but it is a manual and tedious process, with over 20
developers, it is unmanageable.
Does anyone have this issue and have a better suggestion on how to handle
this?
Joe