H
hookturn
I'm reading project help. I want to save a baseline for some specific tasks
as my schedule is not complete.It says under 'roll up baselines' I am not
sure exactly what roll up means. It says if I want baseline data for
selected tasks to be rolled up to those tasks' summary tasks' select the 'to
all summary tasks' check box.
What does roll up do?
thanks
as my schedule is not complete.It says under 'roll up baselines' I am not
sure exactly what roll up means. It says if I want baseline data for
selected tasks to be rolled up to those tasks' summary tasks' select the 'to
all summary tasks' check box.
What does roll up do?
thanks