Roll-up of formulaes

S

Steve Scott

If I have a stoplight formula in a plan does it get overrided by the
stoplight formula in the plan it is consolidated into?
 
G

Gérard Ducouret

Hello Steve,

No, in the consolidated plan, the subproject tasks remain subject to the
subproject.
Hope this helps,

Gérard Ducouret
 