S
Spin-Dizzy
Hi there! I am attempting to use Project to do a sort of Best Case / Average
Case / Worst case analysis using task durations. Basically, I am using the
default duration field to enter the number of hours each task will take in
the average case. I have created custom duration fields for best case and
worst case durations, and I have set their calculation to be "Sum", but I
have found out that it's really just a simple arithmetic sum - it doesn't
account for the fact that independent tasks can run in parallel.
For example, if I have two level-2 tasks, each without any predecessors,
each with a duration of 8 hours, the built-in duration field at level-1
summary correctly calculates to 8 hours because it understands that the tasks
can be done in parallel. Unfortunately, if I enter 8 hours for each task in
the custom duration fields, the level-1 summary shows 16 hours. Because of
this behavior, I cannot rely on the totals at the top of my project plan as a
means of comparing my average case total duration to my best and worst case
total durations.
Does anyone know how to create secondary (and tertiary, etc.) durations that
actually sum based on dependencies?
Any help would be greatly appreciated!
Spin
Case / Worst case analysis using task durations. Basically, I am using the
default duration field to enter the number of hours each task will take in
the average case. I have created custom duration fields for best case and
worst case durations, and I have set their calculation to be "Sum", but I
have found out that it's really just a simple arithmetic sum - it doesn't
account for the fact that independent tasks can run in parallel.
For example, if I have two level-2 tasks, each without any predecessors,
each with a duration of 8 hours, the built-in duration field at level-1
summary correctly calculates to 8 hours because it understands that the tasks
can be done in parallel. Unfortunately, if I enter 8 hours for each task in
the custom duration fields, the level-1 summary shows 16 hours. Because of
this behavior, I cannot rely on the totals at the top of my project plan as a
means of comparing my average case total duration to my best and worst case
total durations.
Does anyone know how to create secondary (and tertiary, etc.) durations that
actually sum based on dependencies?
Any help would be greatly appreciated!
Spin