Rookie question

L

liesto

I think I'm missing a key tenet of MS Project and am hoping that
someone on the board can shed some light.

How does MS project represent 'work' and the allocation of resources to
'work'?

- What does the 'work' field actually represent?
- If a resource is allocated to a task and then removed, why does
'work' drop to 0?

Any help showing me the obvious would be appreciated.

j
 
D

davegb

I think I'm missing a key tenet of MS Project and am hoping that
someone on the board can shed some light.

How does MS project represent 'work' and the allocation of resources to
'work'?

- What does the 'work' field actually represent?
- If a resource is allocated to a task and then removed, why does
'work' drop to 0?

Any help showing me the obvious would be appreciated.

j

Work represents the hours of effort it takes to accomplish the task.
Depending on how resources are assigned, it can vary significantly from
duration. If I have a task of 5d (40h) duration, and assign a single
resource to it, the work will be 40h. This might be for painting a room
or something. OTOH, I might have a task like calling someone to get
some information. It might take 5d to accomplish this, but only 5
minutes of effort during that week. When I assign the resource, I can
tell Project how much work the resource will do during the duration of
the task.
How project handles that information depends on 2 settings. Task Type,
which is "Fixed Work", "Fixed Duration", or "Fixed Units". The
relationship between them is Work = Duration x Units. If duration and
units are in different units, say days and hours, a conversion factor,
in this case 8, needs to be factored in appropriately.
Basically, using default settings, which would be Fixed Units, if you
change duration, work will change to keep the units constant, and vice
versa. Same with the other Task Types. The best way to understand all
this is simply to create a task, a few resources, and assign and remove
the resources while monitoing the variables. After a while, the
relationships become clearer.
The other variable is "Effort Driven". Basically, if this option is
turned on, when I ADD a resource to a task with resources already
assigned, it divvies up the work between them. Each resource I add
takes work from the others already assigned. If you remove resources,
the work is reassigned to the other resources still assigned.
It's a little complicated, but if you play with these settings for an
hour or 2, it'll start to make sense.
Hope this helps in your world.
 
J

JackD

Project works with Tasks and Resources.
When a resource is working on a task it is called an assignment.
Assignments consist of an amount of work that the resource is going to do on
that specific task.
The work on a task consists of the sum of work in all assignments.
When the resource assignment is removed, then that work is removed.
Work represents the number of resource hours/days/weeks/minutes that is
being expended.
Further Project uses the equation Work = Duration * Units to determine what
work is.
Units refers to the number of resource units.
Altering one of the values in the equation will affect at least one of the
other values.
You can see that an increase in work will require a proportional increase in
duration or Units.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top