Rounding up Durations

E

Ed

Hello, I have a project where some activities have a SS+75% relationship for
example and that makes some activities to Start or Finish in half days and so
on, is there a way to round up those halves to full days?

thank you
 
J

JulieS

Hi Ed,

To the best of my knowledge no, there is no way to "round" durations.
The 75% lag is using the predecessor duration * .75 to calculate the
lag.

If you change the lag to full days (i.e. 2 d) that may temporarily solve
some of your concern, but it is fairly normal for tasks to start at
times other than the exact start time of a day.

I hope this helps. Let us know how you get along.

Julie
 