E
Ed
Hello, I have a project where some activities have a SS+75% relationship for
example and that makes some activities to Start or Finish in half days and so
on, is there a way to round up those halves to full days?
thank you
example and that makes some activities to Start or Finish in half days and so
on, is there a way to round up those halves to full days?
thank you