Karen
Our project coordinator insists that we cannot enter time into PWA for the
current week until after she has completed whatever reporting she does using
"Collaborate\Update Project Progress". She says that even if we enter time
and click save changes she will see the numbers. I understood that the
administrator does not get the data until we choose updat all.
What are we doing wrong?