Hi there,
I am using project to schedule total marketing activities for the company
and have following problem:
If I want the process of "writing press release" to range from 1.2.6-1.3.6
BUT the resource assigned to this only needs to spend 1 hour each day on
this- how do I keep the time periond 1.2.6-1.3.6 when i enter 28 hours for
the resource???
Proejct keeps recalculating the total time of project....
Basically, I need to be able to assign different task to different resources
but als odefine a time period in which the activity is running...
Can anyone help?
Thanks ! Rebecca
I am using project to schedule total marketing activities for the company
and have following problem:
If I want the process of "writing press release" to range from 1.2.6-1.3.6
BUT the resource assigned to this only needs to spend 1 hour each day on
this- how do I keep the time periond 1.2.6-1.3.6 when i enter 28 hours for
the resource???
Proejct keeps recalculating the total time of project....
Basically, I need to be able to assign different task to different resources
but als odefine a time period in which the activity is running...
Can anyone help?
Thanks ! Rebecca