I need to schedule an activity to ensure that change tickets have been
approved 5 days (T-5 with T being Move to Production) before move to
production. Is there a way to do this in MS-Project 2002?
What makes it messy is that I need to know the move to production date
(which has other dependencies) before I can calculate the T-5 and the change
ticket approval task falls before the move to production. I can hard code but
would prefer a systemic way to handle this.
Thanks
Earl