Hi John,
Link Task 1 as the predecessor to task 2. Create a new calendar
(Tools>Change Working Time) where only Monday is working time (All other days
are non-working.) Assign the calendar to task 2 (Double click on Task 2 and
on the Advanced tab select the new calendar).
[Note: Task calendars are only available in Project 2000 and later.]
Hope this helps. Let us know how you get along.
Julie
John said:
the monday task will start and end on Monday it will not carry over another day
if the previous task carries over past when the monday task will start it
will have to start the next Monday.
basicly I need a formula where the days of the week have values like sunday
is 1, monday =2 etc..
then I'd use a lag where = the monday task - the previous task