B
_Bob
I have two tasks that each takes 2 hours. Task 2 depends on Task 1. I'm
using Fixed Work task type. The nature of the dependency is finish-to-start
(Task1 must be done first). I can't seem to set Task 1 as the
Finish-to-Start predecessor on Task 2 AND have them start/end in the same
day. I can see if I change the dependency to Start-to-Start they can be
scheduled in the same day. Is that what I have to do despite the nature of
the dependency?
using Fixed Work task type. The nature of the dependency is finish-to-start
(Task1 must be done first). I can't seem to set Task 1 as the
Finish-to-Start predecessor on Task 2 AND have them start/end in the same
day. I can see if I change the dependency to Start-to-Start they can be
scheduled in the same day. Is that what I have to do despite the nature of
the dependency?