A
anton
Hi,
Is there any field that gives the scheduled progress. I can get it by
Tools/tracking/update project and then set 0 to 100% complete....and I'll
get the schedule in the % complete field. Is there an easier way...or more
direct way?
Thanks
Is there any field that gives the scheduled progress. I can get it by
Tools/tracking/update project and then set 0 to 100% complete....and I'll
get the schedule in the % complete field. Is there an easier way...or more
direct way?
Thanks