I am using a contractors Programme of key delivery dates to setup a
commissioning programme for our company. Basically I am working back from
these key dates to look to what needs to be done, the relationship I have
been using is a start to finish relationship which seemed to work fine.
I was however also using a late as possible constraint to move my tasks
forward to this date. This is fine for a simple programme but I found that
for our contractors programme the sub task which drive the completion date
defaults to the larger hammock on the contractors programme.
Any suggestions, was on the right track at the start?
commissioning programme for our company. Basically I am working back from
these key dates to look to what needs to be done, the relationship I have
been using is a start to finish relationship which seemed to work fine.
I was however also using a late as possible constraint to move my tasks
forward to this date. This is fine for a simple programme but I found that
for our contractors programme the sub task which drive the completion date
defaults to the larger hammock on the contractors programme.
Any suggestions, was on the right track at the start?