R
RobW
Hi. I have a Fixed Unit, effort driven task ten days long. I have three
resources assigned to perform this task with varying levels of effort.
Resource one will be on the task for all 10 days, Resource 2 for three days
and Resource 3 for 7 days. I have Resource 1 scheduled for 100% Units,
resource 2 for 30% and Resource 3 for 70%. The result is that Resource 2 is
schedule for 2.4 hours of work/day for 10 days. I'd like Resource 2 to be
allocated 100% of the time for three days. What would be the best way to
accomplish this?
Thanks.
resources assigned to perform this task with varying levels of effort.
Resource one will be on the task for all 10 days, Resource 2 for three days
and Resource 3 for 7 days. I have Resource 1 scheduled for 100% Units,
resource 2 for 30% and Resource 3 for 70%. The result is that Resource 2 is
schedule for 2.4 hours of work/day for 10 days. I'd like Resource 2 to be
allocated 100% of the time for three days. What would be the best way to
accomplish this?
Thanks.