J
Joe
I am managing a software development project. I also
provide Earned Value such as PV, EV, AC (BCWS, BCWP,
ACWP), SPI, and CPI data to upper management. Often
times, there are additional task that need to be added to
a project plan (scope creep) during the project life
cycle. In terms of baselining and earned value data, what
is the best way to track the project plan? For example,
should I baseline new task items as they are added to the
plan after the initial baseline? (Note: I wouldn't re-
baseline the entire project, just the new task items that
were added). Or should I not re-baseline every time a new
task is added. What I want to know is what effect does
either scenario have on the Earned Value data
(specifically SPI and CPI). My goal is to show management
the impact scope creep has to a project plan. If the SPI
and CPI are more impacted by not re-baselining, would want
to do that to show managers the impact.
provide Earned Value such as PV, EV, AC (BCWS, BCWP,
ACWP), SPI, and CPI data to upper management. Often
times, there are additional task that need to be added to
a project plan (scope creep) during the project life
cycle. In terms of baselining and earned value data, what
is the best way to track the project plan? For example,
should I baseline new task items as they are added to the
plan after the initial baseline? (Note: I wouldn't re-
baseline the entire project, just the new task items that
were added). Or should I not re-baseline every time a new
task is added. What I want to know is what effect does
either scenario have on the Earned Value data
(specifically SPI and CPI). My goal is to show management
the impact scope creep has to a project plan. If the SPI
and CPI are more impacted by not re-baselining, would want
to do that to show managers the impact.