H
HarryPMP
I would like to set up a task for project management, that automalically
expands or contracts in duration and work, based on the lenth of the project.
For example, if my project started on a monday, and ended on a friday, the
PM task would be 5 days and 40 hours. Then if the project duration
increased, the PM task would automatically increase, ie if another day was
added, my PM task would be 6 days and 48 hours.
I have tried linking the PM Task in a number of ways, changing task type,
but I have not been able get this done.
The reason I am doing this, is that I want to allocate PM time, 8 hours per
day, for the length of the project, and not have to go back each time I
update the plan.
TIA
Harry R. Alexander, PMP
expands or contracts in duration and work, based on the lenth of the project.
For example, if my project started on a monday, and ended on a friday, the
PM task would be 5 days and 40 hours. Then if the project duration
increased, the PM task would automatically increase, ie if another day was
added, my PM task would be 6 days and 48 hours.
I have tried linking the PM Task in a number of ways, changing task type,
but I have not been able get this done.
The reason I am doing this, is that I want to allocate PM time, 8 hours per
day, for the length of the project, and not have to go back each time I
update the plan.
TIA
Harry R. Alexander, PMP