Set up to enter hours pr, not % complete

R

Russ

Under admin, cust. project web access, I have it set
to "hour per day or week" time period weekly.

But when you go the the timesheet view, the only cell you
can update is the % complete for the task (LH side of
split). I want the user to update the hours the worked per
day for the task (Rh side of split).
 
D

Dale Howard [MVP]

Russ --

You need to have every project manager open every project and click
Collaborate - Publish - Republish Assignments, and then click OK. Doing so
will "push" the new method of tracking progress to each user's PWA
timesheet. Do know this, however: only unstarted task assignments will
show the new method of tracking. In progress task assignments will continue
to use the old method of tracking until they are complete. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 