Where did I miss what he said? Quote "I need task B to start 1 week after
task A starts and end a week after task A ends." Doesn't that imply that
the duration of A and B are equal? If the durations weren't equal and B's
start was offset from A by 1 week, the ends would be offset by some amount
other than 1 week would they not? He also says it appears he needs both a
lag time and a lead time and asks if it is possible. But even asking the
question betrays confusion of just exactly how links work and what lag times
and lead times are in the first place. I explained why it was impossible to
set both lag and lead into the relationship between two tasks at the same
time, provided a work around that would accomplish the scenario he said he
needed, and at the same offered a discussion why he should re-think the
approach he's taking since (IMHO) it's likely to lead to bogus, or at the
very least unrealistic, scheduling in the long run. Just where do you take
exception to that?
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visithttp://
www.mvps.org/project/faqs.htmfor the FAQs
Re-read his post, Steve!
- Show quoted text -