We are using MS Project 2003 and Server. Under TASKS, View My Tasks, View
Options, one of our employees can't access the drop down to view the calendar
to set a date range. When he goes to click the pulldown to view the
calendar...no calendar show up and the field just shows up blank. Could this
be a bug? The rest of us can access the calendar just fine and set date
ranges/units. Thank you in advance.
 