J
Joseph Kiely
Currently, my organization uses the “% work completed†field in Microsoft
Project to calculate earned value. These percentages are multiplied against
a budgeted dollar value in our Earned Value Management System called COBRA to
financially represent how a program is performing in terms of cost and
schedule. Our organization also uses an integration feature in the COBRA
application that integrates project and COBRA in order to pull in the
baseline work identified in the schedule. (No problems here)
The COBRA tool also allows you to use the integration wizard to extract data
from the “remaining work†field which I refer to as an ETC (Estimate to
Complete). The problem is that when you make adjustments to the hours in the
“remaining work†field your “% work completed†changes which distorts your
schedule performance in COBRA. I believe that creating a custom field in
Project would solve my problems but I am not sure how to proceed. Basically,
I would like my percent completes to be calculated based upon my baseline
work since this should never change. This would allow me to make updates to
the remaining work without affecting the % completes I am claiming.
Also, I need to be able to have this custom field roll-up to the summary
task level. I experimented with using the “physical percent complete†field
instead of the “% work completed†field and noticed that it would not roll up
to the summary tasks.
Any help would be greatly appreciated.
Project to calculate earned value. These percentages are multiplied against
a budgeted dollar value in our Earned Value Management System called COBRA to
financially represent how a program is performing in terms of cost and
schedule. Our organization also uses an integration feature in the COBRA
application that integrates project and COBRA in order to pull in the
baseline work identified in the schedule. (No problems here)
The COBRA tool also allows you to use the integration wizard to extract data
from the “remaining work†field which I refer to as an ETC (Estimate to
Complete). The problem is that when you make adjustments to the hours in the
“remaining work†field your “% work completed†changes which distorts your
schedule performance in COBRA. I believe that creating a custom field in
Project would solve my problems but I am not sure how to proceed. Basically,
I would like my percent completes to be calculated based upon my baseline
work since this should never change. This would allow me to make updates to
the remaining work without affecting the % completes I am claiming.
Also, I need to be able to have this custom field roll-up to the summary
task level. I experimented with using the “physical percent complete†field
instead of the “% work completed†field and noticed that it would not roll up
to the summary tasks.
Any help would be greatly appreciated.