I'm in the middle of scheduling a project that will require resources
to be scheduled in 2 12-hour shifts. Because we aren't going to
schedule at the individual level, I'm scheduling by crews. During the
day shift we have 7 crews for this contractor, so I'm assigning the day
shift at 700% allocation. The night shift has 3 crews for this
contractor, so I'm assigning the night shift at 300% allocation.
What I'd like to do is be able to get Project to just allocate the
resources from this contractor at 700% from 6AM - 6PM and at 300% from
6PM - 6AM.
Right now, the only solution I can see is to schedule with the resource
at 24 hours and then shuffle the assignments to the day shift or the
night shift till everything comes out right.
Is there an easier way to do this?
Any other ideas?
Larry
to be scheduled in 2 12-hour shifts. Because we aren't going to
schedule at the individual level, I'm scheduling by crews. During the
day shift we have 7 crews for this contractor, so I'm assigning the day
shift at 700% allocation. The night shift has 3 crews for this
contractor, so I'm assigning the night shift at 300% allocation.
What I'd like to do is be able to get Project to just allocate the
resources from this contractor at 700% from 6AM - 6PM and at 300% from
6PM - 6AM.
Right now, the only solution I can see is to schedule with the resource
at 24 hours and then shuffle the assignments to the day shift or the
night shift till everything comes out right.
Is there an easier way to do this?
Any other ideas?
Larry