Show Resouce in Calendar View

G

Gerald S.

Is there a way to customize the Calendar View in Project 2000 to show the
Resource assigned to a Task.
By default it shows Task Name and Duration

Thanx.
 
M

Mike Glen

Hi Gerald,

Welcome to this Microsoft Project newsgroup :)

Yes - Format/Bar Styles.../and in the Text Fields: type Resource Names. If
you want other fields to show, add a comma and enter the others.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 