Hello Landersman,
When you say "less hours than budgeted" do you mean it took fewer work
(effort) hours or a shorter time (less duration)?
First, I'd suggest showing the Tracking table applied to the task
sheet. If the task was completed in less duration, change the actual
duration to the lower number after marking the task 100% complete.
(If the remaining duration goes above zero, simply zero it out.
If the task took less effort, the tracking table does show actual
work. You could add the remaining work field for ease of use. After
setting the percent complete to 100%, adjust the actual and remaining
work as needed.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project