Showing Tasks and Sub-Tasks in the Calendar View

D

danfrancisco

Hello,

I'm trying to use show both tasks and sub-tasks in the calendar view. It
seems like it only wants to show the sub-tasks but not the high-level one's.
Basically I'm trying to display the same information found in the Gantt Chart
but in a more traditional calendar view. Is this possible?

Thanks,

Dan
 
M

Mike Glen

Hi Dan,

Welcome to this Microsoft Project newsgroup :)

In Calendar view, Format/Bar Styles.../select summary and give it a style
you want.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top