Single level Milestone roll up

F

FreeWill

I am looking for a way to show a rolled up milestone only to the imediate
level. In other words, I want to exclude some milestones that get rolled up
to the top level. Is there a way to do this or will I be forced to rollup
milestones all the way to the top level?
 
J

Jan De Messemaeker

Hi,

No Problem
For all parents but the immediate one, cross out "Show Rolled Up Gantt Bars"
in Task Information, General.
HTH
 
F

FreeWill

Thanks for the sugestion, but it dosent seem to work. Not sure what I am
doing wrong. Also, wouldn't your solution cause all Milestones to not roll
up to the parent level that I crossed out "Show Rolled Up Gantt Bars"? I
would like to select which milestones that rollup to the top level.

Thanks for your help,
Will Visser
 
J

Jan De Messemaeker

Hi,

You can only stop the rolling up at summary task level.
You cannot tell a milestone to rollup only one level.
HTH
 
F

FreeWill

I think I see the part of the problem. Your sugestion will work if I am in
the Normal Gantt view. The problem is that I have set up this project as a
multiple gantt bar view. I did this so that I could track different types of
dates for the same task. When using this view all milestones rollup
regardless of whether I cross out the "Show Rolled up gantt bars" box.

Thanks for your help,
Will Visser
 