Specify task start time

V

Vinayak Bhat

I am using project 2000. I want to specify the tasks time for 30minutes.

e.g. MOndat 10:30AM to 11AM.

How do I do it? Pleae help me.

Vinayak
 
J

Jan De Messemaeker

Hi,

Enter durations as 30 min
Enter date values as 16/6/07 12:21
And to show it all Tools, Options, View, Dtae Format, selet the upper one
(with time of day in the format)
HTH
 
S

Steve House

Except in very rare special circumstances you should never 'specify' a
task's start date/time and/or its end date/time. What you do input is the
task's duration and what you describe is a 30 minute duration task, entered
in the duration column as '30 min'. When you link it to its predecessor and
assign the resource who will do work, Project will determine for you, based
on when the predecessor is done and when the resource's calendar says he is
available, when the task can start and will also calculate from the start
plus the duration when it will end.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top