Split Tasks

I

IanP

I am trying to split a task using Edit / Split Task click mouse etc yet the
task will not split. Am I missing something obvious?
 
M

Mike Glen

Hi Ian,

Welcome to this Microsoft Project newsgroup :)

It should work - is there any constraint stopping the finish date from
moving out? Try splitting from the Task Usage view by entering zero work
where you want to split the task. What version and SP are you using?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
I

IanP

Mike

Many thanks for your reply.

Although the allocation of daily hours can be set through Task Usage and
entering zero work the bar remained solid ie no split.

I am using MS Project Professional 2003 and SP?

Regards

ian P
 
S

Studer

Go to Format / Layout and check if you have the "Show Bar Splits" option on.

This is basic but you never know...

Studer
 
M

Mike Glen

You're welcome, Ian P. :)
Install SP3 and have another try.
Another thought - try Format/Layout... and make sure you click to Show bar
splits.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top