T
Tom
Hi
I am using Project 98 and have assigned 2 tasks to a resource. The resource
has done a portion of task A and is now going to complete task B before
finishing Task A.
I am trying to link the 2 tasks - therefore I want the finished portion of
Task A to link to the beginning of Task B and then to link back to the
unfinished portion of Task A.
Is this possible? I have been looking at the various possibilities and am
drawing a blank
Thanks
Tom
I am using Project 98 and have assigned 2 tasks to a resource. The resource
has done a portion of task A and is now going to complete task B before
finishing Task A.
I am trying to link the 2 tasks - therefore I want the finished portion of
Task A to link to the beginning of Task B and then to link back to the
unfinished portion of Task A.
Is this possible? I have been looking at the various possibilities and am
drawing a blank
Thanks
Tom