I have a single task “Test Software” and resources “testers” tha
consists of 4 testers and contractors of testers that consists of
testers. I would like to have the work on the task applie
proportionally to the pool for tasks to complete ASAP.
A 100 hour test task either fixed units or fixed work with th
resources as testers[400%],contractor[200%] still results in the tim
split with 50 hours to each group. Is there any what to have projec
split the work proportionally with resource groups or do I have to loa
it at the individual level?
I am trying to have an “estimating” plan that has team responsibilit
not individual if possible. ? Ideas
consists of 4 testers and contractors of testers that consists of
testers. I would like to have the work on the task applie
proportionally to the pool for tasks to complete ASAP.
A 100 hour test task either fixed units or fixed work with th
resources as testers[400%],contractor[200%] still results in the tim
split with 50 hours to each group. Is there any what to have projec
split the work proportionally with resource groups or do I have to loa
it at the individual level?
I am trying to have an “estimating” plan that has team responsibilit
not individual if possible. ? Ideas