mcm said:
in the gantt chart why is there a big difference in the start and finish
dates b/w the standard calendar and the 24 hr. calendar?
mcm,
In what context? If you are taking existing tasks with a given duration
and simply switching calendars between standard (8/5) and 24 hour
(24/7), the start and finish dates will change markedly. That is because
the default definition of a "day" in Project is for 8 hours. If you
change the calendar you also need to change the settings under
Tools/Options/Calendar tab.
Hope this helps.
John
Project MVP