We currently do not have our new methodology in place that will provide
information that we can use to create an Enterprise Global Template or to set
up the RBS and Outline Codes. Is it possible to create a standard plan now,
add actuals, etc. and then 're-apply' the data later on to an Enterprise
Global Template that contains RBS and Outline Codes?

Thanks for any advice..
Bill
 
R

Reid McTaggart

Sure. Changing Enterprise Global later will not affect any of the data in
the standard project fields. So, defining Enterprise Outline Codes, RBS,
etc. can be done at any time you like.

Of course, you will want to go back and populate the new fields in any
existing projects and in the Enterprise Resource Pool.
 
B

Bill Noffsinger

Great, thank you Reid.

Reid McTaggart said:
Sure. Changing Enterprise Global later will not affect any of the data in
the standard project fields. So, defining Enterprise Outline Codes, RBS,
etc. can be done at any time you like.

Of course, you will want to go back and populate the new fields in any
existing projects and in the Enterprise Resource Pool.
--
Reid McTaggart
Alegient, Inc., Houston
Project Server Experts
Microsoft Certified Partner
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top