Hi
I know it's possible but can't find the answer:
Resource 1 does task 1 and it ends 19.03.2008
Resource 2 does task 2 and it ends 21.03.2008
Task 3 can only be started, when at least one resource is available
and shall be done by both.
So it should start as soon as one of the dependencies (t1 or t2) is
available
and r2 joins when it is ready.
How can I handle this?
thanks
Kay
 