start date

J

jen m

I am a rookie with this program so bear with me: I have been entering work
hours into project in the task usage window. for some reason one of the tasks
has the same start date as the entire project and if i try to change it then
it changes all the work hours i have entered. I have made it an "as soon as
possible" task and it is 100% done. some other tasks are doing the same thing
but not all.
also: I have taken a couple courses on ms projet but i still find it very
confusing!!! is there any one on one help available in calgary?
 
J

JulieS

Hi Jen,

When you are entering work into the Task Usage view, are you entering data
into the Work field or the Actual Work field?

The task that is scheduled for the start date of the project most likely has
no predecessors and therefore sits at the start date of the project -- there
is no other task driving the start of the task.

If you want to change the start date of a task, enter Actual Work on the
date you want to the task to start. That should move the Actual Start date.

Sorry, I'm not close to Calgary, but I hope that has helped somewhat.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top