I am trying to build my project plan based on total hours. I have set my
task type to fixed duration so that I can enter the time span over more days
than my hours entered. For example, my task may take 12 hours, but it will be
12 hours over a week's time.
My problem is, the summary task isn't adding my fixed hours. Rather it is
adding my days based on general working times set. How can I set it up so the
summary task line adds up the hours correctly?