Rok said:
Hi John,
Thank you for the reply. I wrote that I have a similar problem. but maybe I
was not quite exact and I didn't choose quite right topic.
Ok, I will try again. My problem are not summary tasks but "project summary
task" (Tools/Options/Outline options for .../Show project summary task).
I have in my project some tasks (some main tasks and also some subtasks)
that have influence on entire project duration and have to be considered -
but only for duration of the entire project and for the start of the next
tasks (finish-to-start task link). On the other hand, this tasks will be done
for free and I don’t want their hours and costs to be calculated into the
project summary task. And the resources are the same, which will do also
paid task, so I cant do just another resource name.
So the question is - how can I exclude some task from project summary task?
I already tried with a filter in a task sheet view, but filter only hides
unwanted tasks and they are still calculated in the project summary task .
Thank you
Rok
Rok,
Sorry, I didn't see your reply until today.
A summary line is a summary line and it doesn't matter if it is the top
level summary or an intermediate level summary, they all show and
represent the same thing - summarized data of performance tasks below
them. So, you do NOT have main tasks and subtasks, rather you have
various level of hierarchy but the only REAL tasks are those that
describe some type of activity to be performed in order to complete the
overall schedule plan. These are called performance tasks and they
normally are the only task lines with resources assigned. Everything
else is a summary.
Ok, if you have some performance tasks that will be performed for free,
I first question why they are even included in the plan, but I suppose
if you want to track the resource allocation, it does make some sense to
include them. There are a couple of choices. One is to set the work for
these free tasks to zero. After all, in a "loaded" schedule, work effort
costs money but you don't want to pay for these tasks, so they
effectively have no work. No work hours or costs will be accrued so it
won't contribute to any summary line values. The problem with this
approach is that having no work for these tasks will not allow Project
to track resource allocation (or potential overallocation). A second
approach would be to use the grouping function I described previously
and look only at the data shown on the group summary lines. A third
approach might be to utilize some custom fields and/or VBA to separate
the paid from the free work and show that information in spare fields at
summary level.
John
Project MVP