F
Fiordispina
I have a summary task that has multiple sub-tasks. I changed all of the
sub-task finish dates (and removed all constraints of the sub-tasks) and the
summary task continues to reflect the original finish date (two months later
than new date).
There are no predecessors, no links, no constraints set.
Help please! Thank you.
sub-task finish dates (and removed all constraints of the sub-tasks) and the
summary task continues to reflect the original finish date (two months later
than new date).
There are no predecessors, no links, no constraints set.
Help please! Thank you.