I have read all of the threads on summary task durations and understand in
principle how they are supposed to be calculated. However, in a very large
project I have created, I have several cases where the summary task shows a
duration of 0 hours despite the fact that it is composed of several subtasks
that have a duration of greater than 0 hours. Can anyone explain this
phenomenon??