M
mmaxwell8
MS Project 2000
Let say I have 3 resources A, B and C. A has 20 hours of work on task #1, B
has 20 on Task #2 and C has 20 on Task #3. If the tasks are linked and
indented under a summary task I can view the outline structure in the task
usage view and see the hours for all tasks. In this case, the summary task
will show a total of 60 hours and each task will show 20 hours.
If I filter the view for "using resource A" I will only see Task #1 and the
20 hours for resource A...which is what I would expect. The problem is the
summary row has not been filtered and will still show 60 hours. This doesn't
seem right. Does anyone one know how to fix this?
Let say I have 3 resources A, B and C. A has 20 hours of work on task #1, B
has 20 on Task #2 and C has 20 on Task #3. If the tasks are linked and
indented under a summary task I can view the outline structure in the task
usage view and see the hours for all tasks. In this case, the summary task
will show a total of 60 hours and each task will show 20 hours.
If I filter the view for "using resource A" I will only see Task #1 and the
20 hours for resource A...which is what I would expect. The problem is the
summary row has not been filtered and will still show 60 hours. This doesn't
seem right. Does anyone one know how to fix this?