Summary tasks adding work

S

Scott A

I have a project where the summary tasks are adding 0.5 days to the Work of
the detail tasks. I have removed resources and changed duration to 0 - the
summary task still shows 0.5 days of work.

Any idea on how to fix?
 
S

Scott A

No resources existed on summary task. What I just did was to outdent detail
tasks - that made Work editable on old summary - changed work to zero and
then indented detail again. Now summary task reflects the proper work.

Thanks for reply.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top