Im having trouble displaying summary tasks in "My tasks" in PWA.
The problem is that when i publish my project, instead of having a group of
activities which are part of a summary task, y see each of the tasks as if
they where independent activities. For example:
Summary tasks in Project 2007:
Meeting
---Send e-mail
---Set up equipment
---Have a meeting
Dinner
---Call guests
---Prepare Dinner
---Serve Dinner
What i see in "My tasks" in PWA:
Send e-mail
Set up equipment
Have a meeting
Call guests
Prepare Dinner
Serve Dinner
Could anyone help me fix this?
The problem is that when i publish my project, instead of having a group of
activities which are part of a summary task, y see each of the tasks as if
they where independent activities. For example:
Summary tasks in Project 2007:
Meeting
---Send e-mail
---Set up equipment
---Have a meeting
Dinner
---Call guests
---Prepare Dinner
---Serve Dinner
What i see in "My tasks" in PWA:
Send e-mail
Set up equipment
Have a meeting
Call guests
Prepare Dinner
Serve Dinner
Could anyone help me fix this?