summry task and subtask progress

Y

yousa

how summry task progress can be delinked from subtask. i know that we can
stop progressing summary task by tool-option-manual but then i cannot update
sumarry tsak even maually. please very urgent for me

thanks
yousaf
 
J

John

yousa said:
how summry task progress can be delinked from subtask. i know that we can
stop progressing summary task by tool-option-manual but then i cannot update
sumarry tsak even maually. please very urgent for me

thanks
yousaf

yousaf,
Something you need to understand. A summary line is NOT a task. It is
simply a summary of all the subtasks under it. Therefore, a summary line
does NOT have progress and that is why you cannot "update" it manually.

John
Project MVP
 
S

Steve House

You cannot separate them. In a very real sense, the summary task is only an
abbreviated report that consolidates information about its subordinate
subtasks. It has no independent existence in its own right and every piece
of data about it except its name is dependent on the metrics of its
subtasks. In a properly designed plan, if you could make all the summary
task lines vanish while leaving all the lowest level subtasks in place, all
the work in the project would still get done.
 