Does anyone know of a way to effectively "unassign" or otherwise prevent a
resource from continuing to charge time against a task once their duties are
completed? (We're using Proj Server 2003.) Thanks for any help!
Tim W.
resource from continuing to charge time against a task once their duties are
completed? (We're using Proj Server 2003.) Thanks for any help!
Tim W.