Task are not coming in my task

A

Aniket

Hello

I have published a project with different assigned task to different users.
I am able to see task under "My Task" but my resources are not able to see
their assigned task in "My Task". They are granted as "Team Member" role and
I am as "Project Manager".

Is there something I am missing?

Ashish
 
J

Jonathan Sofer

In the future you should post project server questions on
microsoft.public.project.server.

But to answer your question here, I think you need to verify that your
resources are set as their own "Assignment Owners" in the project plan. You
can include this field in the task usage view and most likely you will see
that they are all set to your name.

Explanation of how this works in PS 2007:
Enterprise resources in PS 2007 require that the "Default Assignment Owner"
value be set to themselves in your system. If this is not set for each
resource on their account then all assignments are defaulted to the person
who created the project plan (you).

So that this doesn't happen on future projects: Make sure all enterprise
resources have themselves set as the "Default Assignment Owner". This value
can only be set via PWA>Edit Resources or PWA>Server Settings>Manage Users.

To fix the current projects: In the schedule, switch to task usage or
resource usage view and include the field "Assignment Owner". Copy the
resource name from name field into the "Assignment Owner" field and
re-publish the schedule.
 