i've assigned a special calendar to the project (work hours from 9am to 5pm,
37.5hrs per week, applying to regular office staff). For a few of the tasks
in the project i would ike to apply a differnet calendar so that work hours
are 9am to 9pm seven days a week and these are staffed by casuals. However,
when the casual task calendar is applied it plots a 6day duration as 4days!
But if I change the 'working hours' to reflect the casual calendar, the rest
of my durations change to calculate for the 12hours day. How do I fix this?