Calendars may be applied to milestones. A milestone is task with 0 duration.
Example, a meeting is always held on a Friday, but all predecessors for that
meeting must be complete as well. How do you handle a situation where the
predecessors do not finish until the following Tuesday and the meeting is
then pushed back a week and not forced to start on Wednesday?
Create a special calendar where the only work days are Thursdays. Create a
series of tasks with appropriate predecessors, etc. These tasks would use a
normal calendar. There will be one additional single milestone "Meeting
Preparation Complete." Assign the special calendar (Thursdays only) to this
task which means it can only complete on a Thursday.
Make the milestone a precessor to the Friday meeting. The Firday meeting
would use the standard (normal, or project) calendar.
--
If this post was helpful, please consider rating it.
Jim
It''s software; it''s not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project